Going solar in Arizona: your utility, permits and solar lease
Solar across Arizona
Energy Company serves homes across all of Arizona. Your utility decides how your solar is credited and how it gets hooked up, so check the name on your bill. The large utilities are Arizona Public Service (APS), Salt River Project (SRP) and Tucson Electric Power (TEP), and Mesa also runs its own electric utility for part of the city.
APS: Phoenix area and much of the state
APS serves about 1.4 million homes and businesses in 11 of Arizona's 15 counties, including a Phoenix metro service area. Its territory runs from Douglas near the border to the Grand Canyon, and from Gila Bend to Payson. In Maricopa County, APS or SRP serves your home depending on your address.
Based on U.S. Energy Information Administration data for September 2025 to August 2026, the average residential price at APS was 17.1 cents per kWh. APS pays for exported solar at an export rate set each year, and your starting rate applies for 10 years from interconnection. See Arizona solar incentives, buyback rates and tax rules for detail.
SRP: Phoenix area and central Arizona
SRP is a community-based, not-for-profit utility serving more than 2 million people in central Arizona, in and around the Valley. In Mesa, homes get power from SRP or the City of Mesa, and Tempe lists both SRP and APS as electric providers for residents. SRP sets its own solar rules.
SRP's average residential price was 14.05 cents per kWh over the same period. Its export plans credit excess energy at 3.45 cents per kWh, and some of its solar plans include monthly demand charges. SRP's hookup timing is under Steps below.
TEP: Tucson area
TEP delivers power to more than 458,000 customers in the Tucson metropolitan area. Its average residential price was 14.92 cents per kWh over the same period. TEP pays for exported solar at an export rate set each year, and customers keep the rate in place when they asked to connect for up to 10 years. TEP's review and meter timing is under Steps below.
Other utilities: city-owned utilities and co-ops
Some Arizona homes get power from a city-owned utility or an electric co-op. These set their own solar rules. If yours isn't named here, the Energy Plan still applies wherever we serve in Arizona, which is the whole state.
The City of Mesa runs its own electric utility for part of the city and uses net metering for homes, applied as a bill credit. If Mesa is your utility, a home system without storage is capped at 5 kW of panels and 5 kW of inverter capacity. With storage, the caps are 10 kW and 11.5 kW. Mesa reviews the application in up to 4 weeks and the finished installation in up to 4 more, then tests the connection and issues a permission-to-operate letter.
Solar permits in Arizona
Your city, town or county issues the solar permit. For cities and towns, state law (A.R.S. 9-468) sets what the permit can ask for: plans showing where the panels go and how they mount, an electrical diagram and the inverter's listing. An engineer's stamp isn't required unless the city explains in writing why one is needed, permit fees can't exceed the cost of issuing the permit, and cities may use an automated online permit platform.
In Phoenix, the city accepts SolarAPP+ approved designs for rooftop systems on single-family homes and duplexes, but batteries can't use that path, and the Fire Department requires a separate permit for solar and battery storage systems.
In Tucson, the city says it issues the permit within 24 hours once a roof-mounted project clears SolarAPP+ and the city application.
In Mesa, certified solar systems under 10,000 square feet installed by a licensed Arizona contractor don't need a construction permit except for new meters or circuits, while a battery or a meter panel upgrade needs a permit from Development Services.
Steps and utility approval times
The order is the same across the state: site review, design, permit, installation, inspection, then the utility's approval and meter.
TEP says it reviews an application within 21 days, reviews the notice of completion within 7 days and sets the meter within 1 to 3 weeks. You then wait for a permission-to-operate email. SRP gives you six months to finish the agreement, installation and commissioning, and the system must be energized within 24 hours of a passed final inspection.
How a solar lease works with an Energy Plan
In Arizona, an Energy Plan is a lease. The state's third-party power purchase agreement authorization covers schools, governments and nonprofits, not homes, and state law covers the lease of home solar systems. A single company designs, finances, installs, monitors and maintains your solar and battery, and you make a fixed monthly lease payment, with any yearly increase set in your agreement up front. Energy Plans have $0 down.
For export rates, programs and tax rules, see Arizona solar incentives, buyback rates and tax rules.
Looking for solar incentive details? See Arizona incentives.
Frequently asked questions
Do you serve my area of Arizona?
Which utility serves my home in the Phoenix area?
Can I lease solar panels in Arizona?
How long do TEP and SRP take to connect solar?
Does the City of Mesa utility limit solar system size?
Do I need a separate permit for a solar battery?
How fast can I get a solar permit in Arizona?