Going solar in California: your utility, permits and Energy Plan

    Solar across California

    Energy Company serves homes across all of California. Your utility decides how your solar is credited and how it gets hooked up to the grid. Most homes get power from one of three large investor-owned utilities, PG&E, SCE or SDG&E, and some cities run their own utility.

    PG&E: Northern and Central California

    PG&E serves most of Northern California, and its county-by-county service list includes San Francisco, San Jose, Oakland and Fresno. Its average residential price from September 2025 to August 2026 was 34.74 cents per kWh, based on U.S. Energy Information Administration data.

    New solar customers go on the state's net billing tariff, which PG&E calls the Solar Billing Plan, and power you send to the grid earns a credit based on its value in each hour. Our California solar incentives page has the detail. PG&E's permission-to-operate timing is under Steps below.

    SCE: Southern, central and coastal California

    SCE serves more than 15 million people across 50,000 square miles of central, coastal and Southern California. Its tariff index of communities includes Long Beach, Irvine, Santa Barbara and San Bernardino. Its average residential price from September 2025 to August 2026 was 31.64 cents per kWh, based on EIA data.

    New SCE solar customers also go on net billing, and SCE sets export prices for 9 years for customers who applied from 2023 through 2027. See our California solar incentives page for detail.

    SDG&E: San Diego and southern Orange counties

    SDG&E serves San Diego and southern Orange counties across a 4,100 square-mile area. Cities in its territory include San Diego, Chula Vista, Oceanside and Escondido, and San Clemente in Orange County. Its average residential price from September 2025 to August 2026 was 47.56 cents per kWh, based on EIA data.

    New SDG&E solar customers go on net billing too. See our California solar incentives page for export credits and charges.

    Other utilities: city-owned utilities and co-ops

    Some California cities run their own electric utility, such as LADWP in Los Angeles and SMUD in Sacramento. City-owned utilities and co-ops set their own solar rules. If yours isn't named here, the Energy Plan still applies wherever we serve in California, which is the whole state.

    LADWP serves Los Angeles, where an Energy Plan is a lease: LADWP's net metering guidelines bar anyone but LADWP from selling energy to its customers and say lease payments can't be based on how much energy the system produces. Its average residential price from September 2025 to August 2026 was 27.88 cents per kWh. LADWP still uses net metering, so surplus power becomes a bill credit that carries forward.

    Once the Los Angeles Department of Building and Safety (LADBS) signs off, LADWP inspects the system and installs a net meter. The system stays off until every inspection passes and the net meter is in. Systems under 10 kW AC with no service upgrade or battery backup may qualify for LADWP's fast track.

    SMUD serves Sacramento. It raised its Solar and Storage Rate export credit from 7.4 to 9.6 cents per kWh, effective June 1.

    Solar permits in California

    Your city or county issues the solar permit. State law (SB 379) requires cities with 50,000 or more residents to offer an automated solar permit. A standard rooftop system can often get an automated or online permit, while a battery, a ground mount, a panel upgrade or a larger system can add plan review.

    In Los Angeles, a rooftop system of 10 kW or less on a one- or two-family home can get its electrical permit online if it meets the city's equipment limits. Larger or more complex systems go to plan check.

    In San Diego, a rooftop system of 38.4 kW AC or less that follows the city's IB-301 template and needs no fire or structural review can be self-issued with no plan review.

    In San Jose, qualifying rooftop projects on single-family, duplex and townhouse properties can download a permit through SJPermits.

    In San Francisco, SolarAPP+ gives an instant electrical permit for a system of 4 kWdc or less with no panel upgrade. Adding a battery, a ground mount or a new panel moves the project to the city's Solar Permit route, with stamped structural drawings.

    In Sacramento, the city uses SolarAPP+ for automated, immediate permits when a project meets its conditions.

    Steps and permission to operate

    Every project follows the same order: a roof and electrical review, a design, a city permit, installation, a city inspection and then the utility's permission to operate. State law (SB 379) required cities with 50,000 or more residents to offer an automated solar permit by September 30, 2023.

    For PG&E homes, the utility says permission to operate typically takes 5 to 10 business days after it has complete paperwork, with a maximum of 30 business days. Never switch the system on before that letter arrives.

    Solar lease or PPA: what your Energy Plan covers

    An Energy Plan is a solar lease or power purchase agreement, and in Los Angeles it is a lease only. With an Energy Plan, one company handles the design, financing, installation, monitoring and upkeep of your solar and battery, and you pay one monthly bill for all of it. With a lease, you make a fixed monthly lease payment, with any yearly increase set in your agreement up front. With a power purchase agreement, the payment can change over the term, and your agreement explains how. Plans start at $0 upfront.

    For export credits, fixed charges and programs, see our California solar incentives page.

    Frequently asked questions

    Do you serve my area of California?
    Yes. We serve homes across California. Your utility, whether PG&E, SCE, SDG&E or a city-owned utility such as LADWP or SMUD, decides how your solar is credited and connected.
    Which utility serves my home?
    PG&E serves most of Northern California, SCE serves central, coastal and Southern California, and SDG&E serves San Diego and southern Orange counties. Some cities, such as Los Angeles and Sacramento, run their own utility.
    How long does PG&E take to give permission to operate?
    PG&E says it typically takes 5 to 10 business days after it has complete paperwork, with a maximum of 30 business days.
    Who turns on a solar system in LADWP's area?
    LADWP. After LADBS finals the permit, LADWP inspects and installs a net meter, and only its installer can unlock the system.
    Can I lease solar panels in Los Angeles?
    Yes. In Los Angeles an Energy Plan is a lease, because LADWP's guidelines bar anyone but LADWP from selling energy to its customers.
    Do California cities offer instant solar permits?
    State law (SB 379) required cities with 50,000 or more residents to offer an automated solar permit by September 30, 2023. San Francisco and Sacramento use SolarAPP+.
    Does a battery change my solar permit?
    It can. In San Francisco, a battery takes the project out of the SolarAPP+ instant path and into the city's Solar Permit route.

    California electricity rates by utility

    Ready to go solar?