Going solar in Minnesota: your utility, permits and solar lease

    Solar across Minnesota

    Energy Company serves homes across all of Minnesota. Your utility decides how your solar is credited and how it gets hooked up, so check the name on your bill. The investor-owned utilities are Xcel Energy (Northern States Power), Minnesota Power (ALLETE) and Otter Tail Power, and large co-ops include Connexus Energy and Dakota Electric Association.

    State law sets the basics of net metering for home systems under 40 kW. You're billed for the net energy the utility supplies, and the utility credits power you send back at a rate set by law and its tariff. Minnesota also has a statewide interconnection process for systems of 10 MW and under.

    Xcel Energy: Minnesota's largest utility

    Xcel Energy, which files in Minnesota as Northern States Power Company, had about 1.23 million residential customers in Minnesota in 2024. Based on U.S. Energy Information Administration data for 2024, the average residential price at Xcel Energy (Northern States Power Co - Minnesota) was 16.98 cents per kWh.

    A home system under 40 kW can choose to be credited for its net excess at the average retail utility energy rate. See Minnesota solar incentives, net metering and tax rules for detail, including Xcel's Solar*Rewards program.

    Minnesota Power (ALLETE)

    ALLETE had about 125,896 residential customers in Minnesota in 2024. Based on U.S. Energy Information Administration data for 2024, the average residential price at ALLETE was 15.66 cents per kWh. Minnesota Power follows the statewide interconnection process, and net metering for home systems under 40 kW follows state law.

    Otter Tail Power

    Otter Tail Power had about 50,118 residential customers in Minnesota in 2024. Based on U.S. Energy Information Administration data for 2024, the average residential price at Otter Tail Power was 11.33 cents per kWh. It also follows the statewide interconnection process and state net metering law for systems under 40 kW.

    Other utilities: city-owned utilities and co-ops

    Many Minnesota homes get power from an electric co-op or a city-owned utility. State law lets these utilities charge solar customers an added fee to recover fixed costs, if the fee is reasonable and backed by a cost study you can request. A co-op or city utility may credit extra power as a kWh credit carried to later bills, and those credits cancel at the end of the calendar year.

    Connexus Energy had about 134,095 residential customers in 2024, at an average residential price of 13.66 cents per kWh, based on U.S. Energy Information Administration data for 2024. Connexus offers net metering for systems under 40 kW, and you choose in your interconnection agreement whether excess energy is bought back or banked as kWh credits. A licensed Minnesota electrical inspector inspects the system, then Connexus does a final inspection and witness test before it can run.

    Dakota Electric Association had about 108,097 residential customers in 2024, at an average residential price of 14.00 cents per kWh. It follows the statewide interconnection process.

    Based on U.S. Energy Information Administration data for 2024, average residential prices were 16.89 cents per kWh at East Central Energy, 17.91 cents at Rochester Public Utilities and 14.59 cents at Wright-Hennepin Cooperative Electric Association.

    If your utility isn't named here, tell us your address and we'll confirm what's available for your home.

    Solar permits in Minnesota

    Your system needs local permits and an electrical inspection. At Connexus, for example, a Minnesota licensed electrical inspector inspects the system before the utility's own final inspection. A 2024 state law gives local governments technical and financial help to speed up permits for home solar and energy storage.

    Steps and utility approval times

    The order is the same across the state: site review, design, permit, installation, inspection, then the utility's approval and meter.

    Under Minnesota's statewide interconnection process, a small system uses the simplified process with an application fee of up to $100. Eligible net metering customers sign the Uniform Statewide Contract, which serves as both your net metering and interconnection agreement, and you have 30 business days to return it. If a utility misses a deadline, it must tell you in writing within 3 business days.

    Some city-owned utilities use a matching municipal process. Under it, the utility confirms receipt within 10 business days, has 20 business days to review, must witness-test within 10 business days of your certificate of completion, and gives written permission to operate within 3 business days of a passed inspection.

    How a solar lease works with an Energy Plan

    In Minnesota, an Energy Plan is a lease. A single company designs, finances, installs, monitors and maintains your solar and battery, and you make a fixed monthly lease payment, with any yearly increase set in your agreement up front. Energy Plans have $0 down.

    For net metering, Solar*Rewards and other programs, see Minnesota solar incentives, net metering and tax rules.

    Frequently asked questions

    Do you serve my area of Minnesota?
    Yes. We serve homes across Minnesota. Your utility, whether Xcel Energy, Minnesota Power, Otter Tail Power, a co-op or a city-owned utility, decides how your solar is credited and connected.
    Which utility serves my home?
    Check your bill. Xcel Energy is the largest, with about 1.23 million residential customers, and co-ops such as Connexus Energy and Dakota Electric serve many more homes.
    Can I lease solar panels in Minnesota?
    Yes. In Minnesota, an Energy Plan is a lease.
    Can my co-op charge an extra fee for solar?
    State law lets co-ops and city-owned utilities charge a reasonable added fee to recover fixed costs, backed by a cost study you can request.
    How long does solar interconnection take in Minnesota?
    It depends on your utility. Under the municipal process, review takes up to 20 business days, and written permission to operate follows within 3 business days of a passed inspection.
    Do I need an electrical inspection for solar in Minnesota?
    Expect one. Connexus, for example, requires an inspection by a licensed Minnesota electrical inspector, then does its own final inspection and witness test before the system can run.
    What size home system qualifies for net metering in Minnesota?
    State net metering rules for homes cover systems under 40 kW.

    Ready to go solar?

    Get a custom solar design tailored to your specific location in Minnesota.