Going solar in Oklahoma: your utility, permits and Energy Plan
Solar across Oklahoma
Energy Company serves homes across all of Oklahoma. Your utility decides how your solar is credited and how it gets hooked up, so check the name on your bill. The large investor-owned utilities are OG&E and Public Service Company of Oklahoma (PSO), and the state also has electric co-ops. A state law and a Corporation Commission rule govern net metering for home solar.
OG&E: Oklahoma City, Norman, Enid and more
OG&E serves customers throughout Oklahoma and western Arkansas. The communities it names in Oklahoma include Oklahoma City, Norman, Enid, Muskogee, Ada and Durant.
In Oklahoma, OG&E credits extra solar on your bill under its Net Energy Billing Option, which requires a time-of-use rate. Extra energy is credited at OG&E's avoided energy cost and carries forward month to month. See Oklahoma solar incentives, net metering and tax rules for detail.
To connect, you need an OG&E account, an approved interconnection application and a system that passes inspection. OG&E reviews a complete net metering application within 30 business days. OG&E's steps are under Steps below.
PSO: Tulsa, Lawton and other towns
PSO serves all of AEP's Oklahoma customers and is headquartered in Tulsa. The towns it lists include Tulsa, Lawton, Broken Arrow, Owasso and Bartlesville.
PSO offers more than one way to credit extra solar. On its net energy metering option, extra generation earns a bill credit based on the generation part of your rate, and credit left after your bill reaches $0 carries to the next month. PSO says most home interconnection requests take less than 35 days. See Oklahoma solar incentives, net metering and tax rules for detail.
Other utilities: city-owned utilities and co-ops
Some Oklahoma homes get power from an electric co-op or a city-owned utility. The Corporation Commission's list of utility contacts includes about ten electric co-ops. If your utility isn't named here, tell us your address and we'll confirm what's available for your home.
Solar permits in Oklahoma
Your city or county handles the solar permit and inspection. The Oklahoma Uniform Building Code Commission sets minimum statewide codes for buildings, and its 2024 editions of the International Residential Code and International Building Code took effect on September 14, 2026.
- Oklahoma City: A roof-mounted home system is filed as a residential solar electrical permit through the city's online portal. The city accepts optional SolarAPP+ review for roof-mounted home systems.
- Midwest City: A city-licensed electrical contractor must pull the permit, the roof assessment must be stamped by a licensed design professional, and final inspections are required.
OG&E asks you to check with your city or town about a final inspection. Where no local government has authority, a licensed electrician or licensed professional engineer inspects the system. PSO asks you to get any local permits and inspections required by law before it verifies the installation.
Steps and utility approval times
The order is the same across the state: site review, design, permit, installation, inspection, then the utility's approval and meter.
At PSO, you apply before installing anything. If your equipment meets its requirements, PSO approves an interconnection service agreement within 35 days of a fully completed application. After installation, including an AC disconnect switch and a generation meter enclosure, and after local permits and inspections, PSO does a field verification. It then installs a two-way meter and a generation meter and tells you to turn on the system, and you sign the agreement.
At OG&E, you apply online. OG&E reviews a complete net metering application within 30 business days, and it can take longer if information is missing or the system needs engineering review. You can't run your system until OG&E approves the application and gives permission to operate. Reprogramming your meter can take up to seven business days after approval.
How a solar lease works with an Energy Plan
In Oklahoma, an Energy Plan is a lease. A 2018 Oklahoma Attorney General opinion found that a company leasing home solar equipment is not a retail electric supplier under the state's certified territory law, while selling the power from a home system is barred outside city limits. PSO and OG&E both describe home solar on a lease. A single company designs, finances, installs, monitors and maintains your solar and battery, and you make a fixed monthly lease payment, with any yearly increase set in your agreement up front. Energy Plans have $0 down.
For net metering, programs and tax rules, see Oklahoma solar incentives, net metering and tax rules.
Looking for solar incentive details? See Oklahoma incentives.
Frequently asked questions
Do you serve my area of Oklahoma?
Which utility serves my home?
Can I lease solar panels in Oklahoma?
Why is an Energy Plan in Oklahoma a lease and not a PPA?
How long does OG&E take to approve solar?
How long does PSO take to approve solar?
Do I need a permit for solar panels in Oklahoma?
Is there a size limit for home solar in Oklahoma?