Going solar in Pennsylvania: your utility, approvals and Energy Plan

    Solar across Pennsylvania

    Energy Company serves homes across all of Pennsylvania. Your utility decides how your solar is credited and how it gets hooked up, so check the name on your bill. The Pennsylvania Public Utility Commission regulates 11 electric utilities, including PECO, PPL Electric Utilities, Duquesne Light, UGI Utilities and FirstEnergy's four Pennsylvania companies, Met-Ed, Penelec, Penn Power and West Penn Power. FirstEnergy now bills these four as rate districts of FirstEnergy Pennsylvania Electric Company.

    Every regulated utility follows the state's net metering rules. Each kilowatt-hour you send to the grid is credited at the full retail rate, and extra credit carries forward. A home system can be up to 50 kW under state law. See Pennsylvania solar incentives and net metering rules for detail.

    PECO: Philadelphia and southeastern Pennsylvania

    PECO serves more than 1.6 million electric customers in southeastern Pennsylvania. That includes the city of Philadelphia, which asks you to apply to PECO for interconnection before you get a solar permit. The Public Utility Commission reports that in 2025 the average PECO home used 708 kWh a month, with an average monthly bill of $150.34.

    PECO reviews home systems of 10 kW or less at Level 1, with a $100 fee and a 25-day timeline. Your installer applies, gets the local permit, and installs after PECO's approval to install. A third-party inspector sends PECO an electrical inspection certificate, PECO installs a two-way meter, and then it issues a Permission to Operate letter.

    PPL Electric Utilities: 29 counties in central and eastern Pennsylvania

    PPL serves about 1.5 million customers in 29 Pennsylvania counties. Its service area includes Allentown, Bethlehem, Harrisburg, Lancaster, Scranton, Wilkes-Barre and Williamsport. In 2025, the average PPL home used 941 kWh a month, with an average monthly bill of $186.88.

    Your contractor applies online for you. PPL says review for a home system under 25 kW "will take only a day or two." After installation, you get your Certificate of Completion and your contractor connects the system. PPL also has guidance for homeowners whose solar is owned by a third party.

    Duquesne Light: Pittsburgh area

    Duquesne Light serves more than 600,000 customers in two counties, including the city of Pittsburgh. In 2025, the average Duquesne Light home used 599 kWh a month, with an average monthly bill of $155.75. It uses net metering under the same state rules.

    FirstEnergy Pennsylvania: Met-Ed, Penelec, Penn Power and West Penn Power

    FirstEnergy Pennsylvania has four rate districts:

    • Met-Ed serves about 592,000 customers in eastern and southeastern Pennsylvania, including the city of Reading. Average 2025 home use was 930 kWh a month, with an average bill of $194.71.
    • Penelec serves about 597,000 customers in northern and central Pennsylvania and western New York, including the city of Altoona. Average 2025 home use was 725 kWh a month, with an average bill of $167.24.
    • Penn Power serves about 173,000 customers in parts of Allegheny, Beaver, Butler, Crawford, Lawrence and Mercer counties, including the city of New Castle. Average 2025 home use was 930 kWh a month, with an average bill of $195.32.
    • West Penn Power serves about 746,000 customers in 24 counties in central and southwestern Pennsylvania, including Greensburg and Latrobe. Average 2025 home use was 946 kWh a month, with an average bill of $172.45.

    All four use one interconnection process. Most home systems fit Level 1: inverter-based, certified and 10 kW or less, with a $100 application fee. You submit the application with a site plan and one-line diagram, install after approval, then send the signed agreement, a Certificate of Completion and evidence of electrical inspection. FirstEnergy then installs a two-way meter, which it says may take several weeks. Extra output is credited at the generation part of your rate.

    UGI Utilities: Luzerne and Wyoming counties

    UGI's electric division serves about 63,000 customers in Luzerne and Wyoming counties. In 2025, the average UGI electric home used 925 kWh a month, with an average monthly bill of $183.79. UGI reviews home systems up to 10 kW at Level 1. You request the application before installing, and after installation you complete inspections, a witness test and the Certificate of Completion.

    Other utilities: city-owned utilities and co-ops

    The Public Utility Commission also regulates three smaller utilities: Citizens' Electric of Lewisburg, Wellsboro Electric and Pike County Light & Power. Pennsylvania's rural electric co-ops serve more than 238,000 homes, businesses and industries, and some towns run their own electric utility. These utilities are not on the commission's list of regulated electric companies. If your utility isn't named here, tell us your address and we'll confirm what's available for your home.

    Solar permits in Pennsylvania

    The Uniform Construction Code is Pennsylvania's statewide building code. The 2018 code editions, as amended for Pennsylvania, took effect February 14, 2022, and the next update took effect January 1, 2026. Over 90% of the state's 2,562 municipalities enforce the code themselves. Where a municipality has opted out, the property owner or contractor hires a state-certified third-party agency for residential inspections.

    Your utility also needs local code approval before final approval, and FirstEnergy asks for evidence of electrical inspection before the system can run. The Public Utility Commission advises contacting your utility before you install.

    Philadelphia: every solar project needs an electrical permit, and the city asks for your PECO interconnection application first. A roof system of 10 kW or less on a one- or two-family home that isn't on the historic register can use an EZ permit, with no plans. EZ permits are issued the same day in person or within 3 business days online. Other applications are reviewed within 20 business days. A licensed electrical inspection agency does the inspections, and the city then issues a Certificate of Approval.

    Pittsburgh: the city's EZ permit pilot covers a listed solar system mounted flat on the roof of an existing one- or two-family home or townhouse, when the electric service needs no upgrade. Eligible applications are issued within one business day. Battery storage, ground mounts and service upgrades need a standard electrical permit. The city lists solar under its residential electrical permit.

    Steps and utility approval times

    The order is the same across the state: site review, design, permit, installation, inspection, then the utility's approval and meter.

    State rules set Level 1 timelines for regulated utilities. Within 10 business days, the utility says whether your application is complete. Within 15 more business days, it checks that the system can connect safely. After it receives your Certificate of Completion, it has 10 business days to hold a witness test, or the test is waived. You then have 30 business days to sign the interconnection agreement.

    Utility examples: PECO lists 25 days for a Level 1 system. PPL says review for a home system under 25 kW takes a day or two. FirstEnergy says its two-way meter installation may take several weeks.

    How a solar lease works with an Energy Plan

    In Pennsylvania, an Energy Plan is a lease. Pennsylvania law defines a customer-generator as a nonutility owner or operator of a net metered system, so a system you lease can still be net metered. With an Energy Plan, one company handles the design, financing, installation, monitoring and upkeep of your solar and battery, and you pay one monthly bill for all of it: a fixed monthly lease payment, with any yearly increase set in your agreement up front. Plans start at $0 down.

    For net metering credits, the price to compare and 2026 rate changes, see Pennsylvania solar incentives and net metering rules.

    Frequently asked questions

    Do you serve my area of Pennsylvania?
    Yes. We serve homes across Pennsylvania. Your utility, whether PECO, PPL, Duquesne Light, a FirstEnergy company, UGI or a local utility, decides how your solar is credited and connected.
    Which utility serves my home?
    Check your bill. PECO serves Philadelphia and southeastern Pennsylvania, PPL serves 29 counties including Allentown, Harrisburg and Scranton, and Duquesne Light serves the Pittsburgh area. FirstEnergy serves homes through Met-Ed, Penelec, Penn Power and West Penn Power.
    Can I lease solar panels in Pennsylvania?
    Yes. State law covers a customer-generator who is a nonutility owner or operator of the system, so a system owned by someone else can still be net metered.
    How long does PECO or PPL take to approve solar?
    PECO lists 25 days for a Level 1 system of 10 kW or less. PPL says review for a home system under 25 kW will take only a day or two.
    How long do Pennsylvania utilities take to review a small solar system?
    State rules give the utility 10 business days to check your application and 15 more to confirm it can connect at Level 1.
    Do I need a permit for solar panels in Philadelphia?
    Yes. Every solar project needs an electrical permit. A roof system of 10 kW or less on a one- or two-family home outside the historic register can use an EZ permit, issued the same day in person or within 3 business days online.
    Do I need an electrical inspection for solar in Pennsylvania?
    Yes. Utilities require local code approval before final approval, and FirstEnergy asks for evidence of electrical inspection. Where a town has opted out of enforcing the building code, a certified third-party agency does residential inspections.