Going solar in Washington: your utility, permits and Energy Plan

    Solar across Washington

    Energy Company serves homes across all of Washington. Your utility decides how your solar is credited and how it gets hooked up, so check the name on your bill. The investor-owned utilities are Puget Sound Energy (PSE), Avista and Pacific Power. Many areas are served by a public utility district, a city-owned utility or a co-op, such as Snohomish County PUD.

    Based on U.S. Energy Information Administration data, Washington's average residential price was 11.90 cents per kWh in 2024 and 13.17 cents per kWh in 2025.

    State law requires every electric utility in Washington to offer net metering, first come, first served, until June 30, 2029 or until net metering reaches 4% of the utility's 1996 peak demand, whichever comes first.

    PSE: the Puget Sound region

    PSE has about 1.26 million electric customers in a 6,000-square-mile service area, mainly in the Puget Sound region of Western Washington.

    PSE offers net metering to residential and commercial customers on its standard rate schedules, for systems up to 100 kW. It isn't available with PSE's time-of-use schedules 307 and 327. Surplus power is banked as a kWh credit for future use, and banked credits expire March 31 each year. See Washington solar incentives and net metering rules for detail.

    To connect, you apply through PSE's online portal and wait for an Approval to Construct. After the electrical permit is finalized, you submit a Notice of Completion, and PSE tests the system, installs any new meter and approves you to energize.

    Avista: eastern Washington

    Avista serves electric customers in eastern Washington and northern Idaho. It offers net metering for systems of 100 kW or less. Surplus power earns kWh credits that carry forward, and the credit bank resets each year on March 31.

    Avista publishes its Washington review clock. Your installer applies online and pays a processing fee of $100 for systems up to 25 kW. Avista confirms it received the application within 5 business days, says whether it's complete within 10 business days, and approves or denies it within 20 business days. After installation, your installer requests permission to energize, and Avista inspects, installs any new meter and approves the system.

    Pacific Power: Yakima, Walla Walla and nearby communities

    Pacific Power's Washington service area covers Yakima, Walla Walla and nearby communities, with 137,262 customers in the state. Its Washington net metering covers systems up to 100 kW. Surplus power becomes a kWh credit on your next bill, and credits left after the March billing period each year go to the utility.

    Pacific Power has proposed replacing net metering with net billing for new applicants, with an effective date of February 1, 2027. The proposal is still before state regulators. Pacific Power says customers who submit a complete application by February 1, 2027 can stay on net metering. See Washington solar incentives and net metering rules for detail.

    You apply online with the planned system and a photo of your meter, get permits and install, but don't switch the system on. After you upload the inspection and sign, Pacific Power says to allow 7 to 10 days for the meter, and some projects can take longer than 70 business days.

    Portland General Electric has applied to take over Pacific Power's Washington service area. State regulators are reviewing the application.

    Other utilities: PUDs, city-owned utilities and co-ops

    Public utility districts, city-owned utilities and co-ops set their own solar rules within state law, and they may adopt their own rate once the state net metering window closes.

    Snohomish County PUD serves Snohomish County and Camano Island, including Everett, Lynnwood, Marysville, Edmonds, Monroe and Arlington, and it had 346,094 residential customers in 2024. It uses net metering for systems under 100 kW. It allows up to 2 weeks to process an application, charges an $85 processing fee, and sends an Approval to Construct by email. After the final electrical permit, you submit a Notice of Completion, and the PUD emails permission to operate.

    If your utility isn't named here, tell us your address and we'll confirm what's available for your home.

    Solar permits in Washington

    Your solar installation needs an electrical permit. In Washington, whoever does the electrical work must get the permit before starting. An inspection must be requested before the work is covered, and no later than 3 business days after the work is done or 1 business day after any part is energized, whichever comes first. The state Department of Labor & Industries issues most electrical permits, but some cities, including Bellevue, Bellingham, Everett, Kirkland, Olympia, Spokane and Vancouver, issue permits and inspect within their own limits.

    In Bellevue, every solar system needs an electrical permit, and a building permit isn't required for a rooftop system on a house when the installer confirms conditions such as a lightweight roof, a mounting system engineered for solar and panels no more than 18 inches above the roof.

    In Kirkland, you apply for the electrical permit through MyBuildingPermit.com, and the city requires a pre-construction inspection and a final inspection.

    PSE and Snohomish County PUD both wait for the final electrical permit before you file your Notice of Completion.

    Steps and utility approval times

    The order is the same across the state: site review, design, permit, installation, inspection, then the utility's approval and meter.

    Avista approves or denies a complete application within 20 business days. Snohomish County PUD allows up to 2 weeks to review an application. Pacific Power says to allow 7 to 10 days for the meter after you submit your inspection. PSE lists its steps but no review times.

    Solar lease or PPA: what your Energy Plan covers

    With PSE, Avista and Pacific Power, an Energy Plan is a solar lease or power purchase agreement. With other Washington utilities, it's a lease. Washington's 2024 solar consumer protection law covers homeowners offered a solar energy system lease. With an Energy Plan, one company designs, finances, installs, monitors and maintains your solar and battery, for one monthly payment. With a lease, you make a fixed monthly lease payment, with any yearly increase set in your agreement up front. With a power purchase agreement, your payment can change, as your agreement explains. Energy Plans have $0 down.

    For net metering rules and programs, see Washington solar incentives and net metering rules.

    Frequently asked questions

    Do you serve my area of Washington?
    Yes. We serve homes across Washington. Your utility decides how your solar is credited and connected. If it isn't named here, tell us your address and we'll confirm what's available.
    Which utility serves my home?
    Check your bill. PSE serves the Puget Sound region, Avista serves eastern Washington, and Pacific Power serves Yakima, Walla Walla and nearby communities. Many homes are served by a public utility district or city-owned utility, such as Snohomish County PUD.
    Can I lease solar panels in Washington?
    Yes. The state's 2024 solar consumer protection law covers solar leases offered to homeowners. With PSE, Avista and Pacific Power, an Energy Plan can also be a power purchase agreement.
    Is net metering still available in Washington?
    Yes. State law requires utilities to offer it until June 30, 2029, or until net metering reaches 4% of the utility's 1996 peak demand, whichever comes first. Pacific Power has proposed net billing for applications after February 1, 2027.
    Who gets the electrical permit for solar in Washington?
    Whoever does the electrical work gets the permit before starting, and must request inspection within 3 business days of finishing. Some cities issue their own electrical permits.
    How long does Avista take to approve solar?
    Avista approves or denies a complete application within 20 business days.
    How long does Snohomish County PUD take to approve solar?
    It allows up to 2 weeks to process an application, then emails an Approval to Construct.
    When can I turn my system on?
    After the utility approves it. PSE approves you to energize after testing, Avista approves after its inspection, and Snohomish County PUD emails permission to operate.