Delaware solar incentives, net metering and tax rules
Net metering under Delaware law
Delaware law requires net metering at Delmarva Power, and it directs the electric co-op and town utilities to adopt their own net metering rules. A residential system can be up to 25 kW and can't be designed to produce more than 110% of your expected yearly use.
Since January 1, 2024, each extra kilowatt-hour you send to the grid is valued at the per-kWh supply and distribution charges, not counting societal benefits program charges. Credits carry into later months. They don't reduce fixed monthly customer charges. The state rule says unused credits left at the end of the yearly billing period go back to the utility, with no payment.
DEC, Dover and Newark credits
DEC banks extra output as kilowatt-hours for future bills. It says banked kilowatt-hours expire after the March billing period each year, and its $16 customer charge applies every month.
The City of Dover credits power you send back at the city's current rate for your class of service, applied to the next month's bill. For applications after October 13, 2022, Dover may bill up to $200 for a residential two-way meter, and there is no application fee.
The City of Newark carries extra credits forward through its billing year, April 1 to March 31, and then resets them.
Rate case to watch: Delmarva Power
Delmarva Power filed for a base rate increase on December 9, 2025, including a rise in the monthly customer charge from $13.50 to $15.94. Its final update, filed August 31, 2026, asks for $75,829,980, or 24.25%. For a home using 834 kWh a month, distribution base rates would rise about $11.63 a month.
Delmarva put half of its proposed increase into effect on July 9, 2026, subject to refund with interest (PSC Docket No. 25-1555). The state expected a decision late in 2026.
Delaware programs and their status
The Green Energy Program, run by the Department of Natural Resources and Environmental Control (DNREC), is open only to Delmarva Power customers. DNREC says high demand means some approved grants may be queued for payment until funds are available, and three new offerings launched as of August 10, 2026.
Its Solar + Storage Pilot, effective August 11, 2026, pays residential applicants $250 per kWh of battery storage, up to $6,000 and no more than 50% of the storage cost. The battery must be owned by the applicant, so leased or third-party-owned batteries don't qualify.
DEC's solar grants, handled through Energize Delaware since 2024, are not available for leased systems. The City of Newark says the Delaware Municipal Electric Corporation offers residential green energy grants of up to $3,500.
On September 1, 2026, the governor announced Delaware SHINES, a state program pairing larger Green Energy Fund grants, low-to-moderate income solar grants and a new Delaware Energy Hub at solar.delaware.gov.
Solar renewable energy credits (SRECs)
Delaware runs a yearly SREC procurement for Energize Delaware and Delmarva Power. The 2025 round accepted bids from November 3 to November 14, 2025. With a leased system, the third-party owner owns the SRECs.
Federal tax credit
The federal residential clean energy credit (25D) is not allowed for expenditures after December 31, 2025, and an expenditure counts as made when installation is complete.
With an Energy Plan, you have one company for design, financing, installation, monitoring and maintenance, and one monthly payment. For hookup steps and permits, see Going solar in Delaware.
Looking for solar coverage in Delaware? See solar service in Delaware.
Frequently asked questions
Does Delaware have net metering?
What happens to unused solar credits in Delaware?
Is the Delmarva rate case decided?
Are there battery incentives in Delaware?
Can I get a Green Energy Program grant with a solar lease?
Who gets the SRECs from a leased system?
Ready to go solar?
Get a custom solar design tailored to your specific location in Delaware.